At column 29 of the 500kV 3-section circuit line from Nam Dinh 1 Thermal Power Plant to Pho Noi, Hung Yen province, there are currently about 20 construction engineers. And in hot weather of 40 degrees, these engineers still have to work continuously for about 10 hours/day. Up to this point, they have completed the installation of 60/69m of electric pole height.
They are Viettel Construction's engineers mobilized from localities across the country. This is the first time Viettel Construction technical staff have constructed high voltage electric poles. But with many years of experience in constructing telecommunications poles, Viettel Construction believes that it will ensure progress and quality.
Image of Viettel Construction personnel rushing to construct the project in hot weather
“This telecommunications pole and 500kV electric pole are similar in design and technique. As for the difference in workload, there will be many more telecommunications towers. This is a key national project, so we are very proud to contribute to the construction of this trunk road and complete it on schedule," Mr. Nguyen Van Tan - Viettel Construction Nam Dinh employee shared.
Mobilize all resources for the 500kV circuit 3 project
Up to this point, all 1,177 pier foundation positions of the 500kV circuit 3 line have completed foundation construction and are in the stage of erecting poles and wiring. To quickly complete the items and complete energization by the end of June, it is necessary to mobilize all resources with construction experience.
Although it has supported hundreds of human resources involved in constructing poles and wiring at locations of the 500kV circuit 3 line, Viettel Construction will continue to mobilize more human resources to support in the near future.
Mr. Dang Van Chung - Director of Viettel Construction B2B Construction Center said: "We have selected our best personnel nationwide to bring here to organize project construction. Currently, we are mobilizing 150 human resources and are mobilizing another 50 human resources to serve the project."
Mr. Dang Van Chung - Director of Viettel Construction B2B Construction Center
The departments and unions of the localities where the line passes through have also planned to support the electricity industry to soon complete the project. Mr. Nguyen Ngoc Luong - Permanent Secretary of the Central Youth Union said: "Up to this point, almost all provinces and cities have had specific tasks, time, location and resources to focus on implementation. About 300 youth volunteer teams have been established with about 4,000 young people participating."
In the coming time, 9 local provincial unions will carry out tasks such as relocating assets, architectural works, and trees to hand over the site, supporting transportation, and arranging materials for construction work.
In order to ensure the quality and progress of the 500kV circuit 3 line project, in Official Dispatch No. 55, Prime Minister Pham Minh Chinh requested localities with passing projects to mobilize available resources and provide maximum support. to best organize logistics, accommodation, and activities. At the same time, mobilize youth union members to promote the spirit of impulsivity and youth, "you don't need young people, it's hard to have young people", with the common goal of completing and energizing the 500kV circuit 3 line.