Despite the complicated development of the Covid-19 epidemic, Viettel Construction and Novaland investor still strive to speed up the construction progress of the Aqua City project, realizing the commitment to put the urban area into operation in 2023. The Aqua City project itself has significantly increased in value right after a series of key projects were finalized and deployed.
Viettel Construction has only started construction since October 2021, but the Corporation has received great trust from the Investor, signing 02 consecutive contracts with a total of 300 villas (106 apartments). villa 7A2 and 124 low-rise villas in zone 7A3).
Images of construction area of Viettel Construction in Aqua City
Ensuring the project progress in the face of the epidemic is not very favorable for Viettel Construction, but the Corporation has put into use cemboard as formwork for floor beams on the 1st floor, speeding up the formwork progress. Use GFRC sheet to complete the façade only. Ensure the quality factor and follow the progress set by the Investor. Specifically:
Contract for 124 units:
- Implemented 08 lots, completed the foundation 48/124 units.
- Completed the underground tank 46/124 units.
Contract for 106 units:
- Started construction of 05 lots, completed the ground floor of the first floor of 63 apartments.
- Pouring the roof of the 2nd floor at 31 villas.
Plan for January 2022:
- Deploying concrete pouring of floor beams on the 2nd floor: 84/106 units.
- Deploying concrete pouring of floor beams on the 3rd floor: 40/106 units.
- Deploying concrete pouring of floor beams on the 2nd floor: 84/106 units.
On the basis of the trust that Viettel Construction has built up during 26 years of establishment and development, the Corporation will become a reliable companion with Novaland Investor in the long term and the journey of bringing value to customers. around the country.